Monday, March 27, 2017

Weekend Duty Blog
March 10th, 11th, and 12th 2017
Amadeo and Soyoung
Friday

Friday started off with Jeff showing us around and answering any questions we needed for the weekend to come. We’ve done this before and it was mostly the same type of tasks except different crops. We put out the sticky cards as the first priority to monitor any pests that may be lurking in the crop. Our first job was walking the crop, we started at one end and working our way out. It was the Petunias and Elephant ears that were first, we put the fertilizer through the Dosatron and got started, there were not many that needed water but it was a good idea to check. After those it was the hanging baskets, 4” pots and everything else (excluding the hydrangeas). We were making sure to keep switching over the fertilizer’s using the Dosatron. Lastly we walked and spot watered the Hydrangea crop, the white Hydrangeas were coming in very full, with the pinks and blues trailing behind with only a few blossoming. Our time spent in the greenhouse passed and we moved onto our second task which was cleaning out the germination chamber. We took out all the cuttings and the metal plates that hold the trays elevated and scrubbed everything to get all the green moss/mould/algae off. It was a task that needed our noses plugged, but we pushed through and got it spotless.




 The chamber was spotless and smelling better. The next task we were told to do was to clean out and remove the soil from the Elephant ear bulb crates. There were 5-6 bulb crates and we took out all the soil in each and cleaned up the bulbs themselves and put them into a single crate. In between our jobs we had a few customers come in and buy some Hydrangeas. We then began to transplant some cuttings into 4” pots. We managed to get 1 full tray of transplants. Towards the end of the day we checked on the crop once more and then closed the till for the end of the day. The last hour was cleaning the potting room from the mess we made from our previous job, then locked up and ended our first day of weekend duty.


Saturday

Saturday started off the same as Friday, we walked the crop and checked for any dryness in the crops. Everything seemed okay and we spot watered what we had to. Our first major task was to update and add to the plant cutting, 4” pot and hanging basket list. We first counted all the cuttings to see if they were the right number and updated the number if need be. The 4” pots were counted and updated as well then we had to make any cuttings we could off of the hanging baskets if it wasn’t on the list already. We managed to get a good number of cuttings off of the hanging baskets we picked out






 The large planters in front of the bookstore were next on the list so we took the Aquamate out there and started off by picking out any Tulips that were dead and pruning out dead foliage in the planters. We watered each planter and worked on dusting off the leaves in the canopy. We were using a plant leaf cleaner and wiping off with rags, it was surprising how dusty the plant was. Some basic pruning on the tree by cutting out some half dead limbs to give it a cleaner look. Back to the greenhouse again we went to go look at the crop and since the sun was out a bit it heated up the greenhouse enough to dry out some of the hydrangeas and we noticed some started to droop. We quickly added water to the ones that looked wilted and checked the rest. They were back up and looking lively by the end of the day



About 30 minutes before closing down the cash register our first customer came in and snagged a white Hydrangea and were quickly on their way. After closing up the cash and bringing in the signs we cleaned the floors and washed some of the pots we used and locked up.


Sunday

It was our final day in the greenhouse and we started it like usual with a crop walk and spot water. The Hydrangeas were looking nice today and we saw a few more blooms and colours coming out. We took down our sticky cards that were put up on Friday and noticed very little bug activity. There about 4 fungus Gnats spread out over 4 cards, probably because of the watering were doing. This was the beginning of the pest-monitoring sheet because we still had to do our EC/pH readings. The readings were OK and we wrote out our findings. Towards the end of the day we made a run to the compost because we had a bunch of old soil and plant material from the other days and came back to start cleaning. We started in the greenhouse and working our way out to the potting room. Only one customer came in and bought two blue Hydrangeas towards the end of the day. There were a few more house cleaning things we tended to then we headed out.

Thursday, March 9, 2017

Greenhouse Duty Blog

Friday March 3rd, 2017
            On Friday March 3rd, Nick and Brandon arrived to the greenhouse and met with Jeff to go over the tasks for the weekend. There were jobs that we weren’t 100% sure about and had some questions so Jeff helped us out and answered whatever questions we had about our greenhouse weekend duty. To start the day we have a checklist that needs to be completed before anything else can be done. We have to check the temperatures in the greenhouse and make sure the priva system is working fully. Also we made sure the germination chamber had water in the bottom of it. We walked the crop to check and see if all the plants were moist or if any needed water.




Next, we opened the till in case we had any plant sales during the day. After we started spot watering the hydrangeas where it was needed, then we did an aluminum sulphate drench on the blue hydrangeas. After we were done the drench, we moved the elephant ears into new 4 inch pots. We filled the pots with soil and put them onto flats. We moved them onto one of the racks closer to the window and made sure we watered them.





Next we brought out a rolling rack and got the wrapping down from upstairs and placed the wrapping onto the rolling rack. There were pots in the garage that were being filled on Wednesday and didn’t get finished, so Jeff asked us to fill the rest of them up and stack them neatly on rolling racks. We ran out of HP pro mix so we got a new bag out the greenhouse and emptied it into the appropriate bin. We had to bring another bag into the greenhouse after we took one out so it has time to thaw out for when we need it next. After we were done that, we walked the crop again to make sure everything had water. Then it was time to clean up and close the greenhouse.

Saturday March 4th


On Saturday we worked on some interior plants. We had to dust the big ficus plants in front of the bookstore, dusted the 2 ficus plants in T building, replanted the palm in the D corridor, and watered the plants in the library. When we first got to the greenhouse we did our morning checklist and walked the crop. We noticed the hydrangeas were getting a little dry, so we watered them all. Throughout the day we checked the crop a lot because it was sunny and we wanted to make sure no plants were drying out and that they all had enough water. We started cleaning the hydrangea leaves as well. Before we left we did another check of everything and did our end of the day checklist.

Sunday March 5th
On Sunday we showed up and did our morning checklist and walked the crop. We spot watered a lot of the plants. Sunday we finished cleaning the leaves on the hydrangeas. It took us most of the morning to complete.




After a lunch break we walked the crop and spot watered the plants that needed water. The elephant ears needed water so we fertilized and watered them. We also noticed that a couple of the elephant ears needed some more soil. We grabbed scoops of the pro mix HP and topped up the plants that needed the extra soil. Next we did our PH and EC readings on the hydrangeas. The PH levels were a little high on the pink and white hydrangeas but the EC readings were all in check. We recorded all of the readings. Sunday afternoon, we completed our Insect and Disease Monitoring report. We recorded everything we needed to. Sunday afternoon we did a really deep clean in the greenhouse and in the potting room. There were pots that needed to be washed so we did that as well. We started by sweeping all the floors and picking up all the dust and dirt that was on the floor and put it all into the compost bin. We emptied the compost bin into the RTV. Next we washed off the tables with bleach and water and scrubbed them clean. After all of that was completed we walked the crop and watered one last time. Next it was time to wash the floors. We sprayed them all down with water and made sure we didn’t miss any spots on the floor. We used squeegees to scrub the floor and move the water into the drains. After we were done cleaning up, we put the wet floor signs out so no one would slip on the wet floor. We completed the Priva chart analysis and handed it in as well. Lastly we did out closing checklist. This completes our weekend greenhouse duty. We learned lots and worked well together on everything.


Nick Hunt and Brandon Velda


Wednesday, March 1, 2017


Greenhouse Duty Blog
February 24-26 2017 
Jenn and James


On Friday, February 24th, 2017 after our instruction from Adrienne and Jeff, we checked the PRIVA system and made notes on the temperature ranges within the greenhouse. We then repotted the red & white petunias and made sure there was at least a lip between the top of the pot and the top of the soil so the water didn’t run out of the pots. This ensures the petunias are getting the amount of food and water they need to thrive. Then we placed only the red petunias on the heat mats to promote quicker root growth so they’re rooted enough to be planted in their hanging baskets. Next week will be the white petunias turn on the heat mat for the same reason. Most of the day consisted of repotting petunias, there were a few moments where customers walked in to see what was for sale. But unfortunately, no sales were made during the whole greenhouse duty. At the end of the day we made notes on the functionality and temperatures of the greenhouse. PRIVA system functions were also recorded.




On Saturday, February 25th, 2017, I immediately went to finish off repotting the last 40 or so white Petunias, while Jenn checked the crop for watering requirements and any kind of issues as well as checked the PRIVA system. We then made fertilizer for the hydrangeas, and root promoting fertilizer for the petunias. The two batches were made carefully and safely. As Jenn cleaned out the outside storage area, I collected the Pro-mix (with some help from Jenn) and placed them under the far benches within the greenhouse so they were thawed out when the classes need them for various tasks. After completing the job, Jenn and I went to tackle the 3 Ficus trees, out front of the bookstore.
Picture 3




They needed to be watered and the under plantings needed some tending as well. We had to apply a “leaf shiner” to the leaves of the Ficus, while removing thick amounts of dust on the leaf’s surface. This took up a large portion of the morning, leading up to lunch, and then continued a little longer after lunch. Jenn had already previously watered the hydrangeas so that an hour afterwards, we could start recording data for the E.C. & pH readings. When taking notes and data, there weren’t too many differences from previous recordings. This made sense as the crop seems to be thriving well. When this was finished, we cleaned/tidied up the greenhouse a little to bring us to the closing time, where we then had to make notes on the temperature from the PRIVA system. We also had to list all functioning apparatuses around the greenhouse to make sure nothing was out of place and/or working improperly.
On Sunday, February 26th, 2017, Jenn and I checked the PRIVA system, the thermometer within the greenhouse and the temperature readings with the infrared gun. Notes were recorded and we then discussed on what tasks would be completed by whom. First task I completed was re-potting the established cuttings from inside the propagation chamber while Jenn made a tray of Tradescantia cuttings for a client order. I then went on to collect cuttings from the stock baskets for cuddy’s. There was no way of obtaining the rooting hormone powder, due to the door being locked. I then improvised, with the suggestion from Jenn, that ‘Coleus’ plants are very easily propagated without the hormone powder, and began to take cuttings only from a group of different Coleus cultivars.
Picture 4




While I was completing this task, Jenn moved onto creating new succulent collections that are for sale in our greenhouse.
Picture 5




Once the cuttings were obtained, I made labels for them, watered them and then placed them into the propagation chamber. I then went out to clean the tractor bay and tidied up loose tools and pots. After doing this, Jenn suggested it was time to take out the compost and deposit the contents within the dumping area, located at the North-West end of the college campus. Upon our return, we then took the left over miscellaneous potting mix and placed into a garden bed located along M building, adjacent to the greenhouse. We then finished the day off with a thorough cleaning of the entire greenhouse, making sure to squeegee most of the floor underneath the crop to avoid too high of humidity levels from using water to remove the built-up dirt. Of course PRIVA systems and other functions of the greenhouse were checked over to make sure all were working correctly.
Overall, the weekend went smoothly. We’re excited about being able to sell the hydrangea crop soon and are looking forward to seeing more of the blooms burst with colour.







Friday, February 24, 2017

Weekend Duty Blog - February 17-19, 2017
Lexi Drenth & Scott Pollock

            During our weekend duty, we learned a lot and did quite a bit. We will be going over what we did on each day, including when we opened and closed and a bit about the field trip on Friday.

            On Friday, both Scott and Lexi participated in the field trip to Landscape Ontario’s Plant Symposium at the Best Western Lamplighter Inn in London. During our breaks, we walked around and looked at all the ponds by the pool. We were looking at some plants that we just learned about in our Plant ID class a couple of weeks prior. At lunch, we discussed about leaving the field trip early to go back to the greenhouse and start our work early. We had a couple hours head start potting up the Supertunia plugs. After we put away our stuff, we didn’t do an efficient clean because we knew we were coming back tomorrow and making the same mess.

            On Saturday morning, we arrived at 7:45am and signed in and started thinking about how we were going to get through all the work within the next two days. After we walked the crop, we put our four sticky cards out throughout the crop. We started with going through the crop in the greenhouse to look for dry spots and/or imperfections with the crop, like wilting or broken leaves. We fertilized the hydrangea crop right in the morning so then we could test the EC and pH levels, but after we set up eight plants, we realized that we did not get our professors to get the deionized water out of the chemical storage closet before they left on Friday.  We called our supervisor for advice and realized we could not do it so we could not partake in doing these tests. We moved past that and we had all the Supertunia plugs to pot up in the four-inch pots. 



We made up a total of 605 pots with one plug in each and separated into trays based on their colours. We had ordered red and white, all based on Canada’s 150th Anniversary this summer. We were going through so much potting mix that we had to make up two extra bags of pro-mix. It took us up to lunchtime to finish and organize them. After lunch, Lexi potted up some orange chrysanthemum pots as Scott put the Pretoria Canna Lillies in the pots half deep. As Scott did that, Lexi was making up tags for each of the pots.



 As soon as they were done, Lexi put all the information on the sheets of papers on the seed fridge. We took a walk to the library with the watering jug, there are three plants in the back that were dry. We finished the day off by filling out our paperwork, starting with the IPM sheet and the PRIVA sheets.

            When we opened up on Sunday, we started by walking the crop again to check for dry spots and remove any debris. When we were done with that, Lexi started to clean the potting room and Scott worked in the greenhouse and cleaned the outside storage space. Before Lexi started cleaning the potting room, she pinched the Tradescantia in the four-inch pots. We spent most of the morning cleaning. Scott squeegeed the floors in the greenhouse after he watered some of the plants. He squeegeed the floors into the floor drains, after he completely wiped down the floors, swept and made sure all the hoses were rolled up properly and to make sure it looked organized. As Scott was doing that, Lexi was cleaning the potting room, she was cleaning every crack and crevice. She organized everything so well; it looked like a completely new room. 



After we had lunch, we took the water tank and two ladders and we started dusting the leaves on the three ficus trees in front of the bookstore. Lexi was wiping them down with a soap and water mix and Scott was using a leaf shine liquid. We spent our time doing them, we made sure that the leaves that were showing were really clean but we tried to get the really tall ones and the ones deep in the trees. We didn’t want to spend a ton of time each of the trees but we did spend a couple hours doing all of them.



At the end of the day, we spent the rest of the day finishing the PRIVA sheets, IPM sheets and uploading the pictures onto the computer.



        
        By the end of our weekend duty, we learned a couple things about the humidity levels in the greenhouse. We learned that whenever we have a question no matter how small or big but we have to be willing to ask the question. There were a couple points of the weekend that we had to call our supervisors for the answers, which is what they are there for. It is very risky putting students in charge of a whole greenhouse for a couple days, but it is a very good learning experience for us all to do a weekend now and then. 





Monday, February 13, 2017

Greenhouse Blog – Weekend Duty Feb 10 – 12                                            
Sean Fitzpatrick and Caitlin McPhee

Friday Feb 10 2017, Sean and I arrived to the Fanshawe greenhouse ready for action. Even though it was a bit gloomy and not very warm out our motivation was high. We began our day with a debriefing for the weekend by the resident greenhouse technician Jeff Rowley. While walking the crop we checked for unhappy plants and broken windows. We also made sure the germination chamber was filled with water to ensure the humidity in each chamber was acceptable. While walking the crop Sean and I placed sticky cards to measure pest levels in greenhouse, placing three yellow and one blue stick card. We opened the POS system for sales of cacti and succulents. Throughout the day we had many happy customers in the greenhouse. After cutting back the Colocasia, with the help of Jeff we applied aluminum sulphate to blue hydrangeas. Lunch time quickly came and as we re energized ourselves and I wrote down the rest of the duties for weekend. Lucas our Cuddy Farms Horticulture Technician dropped by with some odd jobs for us to do. He asked us to stain the trellis being used in the spring and allowed them to dry in our tractor bay. An hour after we watered the hydrangeas Sean and I took EC and pH readings which we found the pH was low on the blue hydrangeas while EC levels were acceptable. While working in the greenhouse we noticed some of our stock basket plants were missing labels, so we identified the missing plant names, took pictures, recorded them, and placed them in their rightful benches. That afternoon the clouds never seemed like they would go away but for a brief moment the sunlight in greenhouse beaming down on all the plants it was as if the plants were smiling back at us! Later that afternoon after re-walking the crop Sean and I noticed aphids on the base of the Colocasia, and we were able to stream a video of aphids moving on some foliage. We then cut the dead foliage off, cleaned and treated the plants with insecticidal soap. Sean later quarantined the plants in the tractor bay. Near the end of the day we shut down the sales, cleaned up and sterilized all the tools that were used including the benches in the potting room. 5:00 o’clock came and Sean and I signed out, dropped off the keys and left with a hard works day behind us. 






  
Saturday February 11th 201
Sean and I arrived bright and early to the greenhouse on a very cloudy and windy morning with lots of jobs to do for the day. First we checked that all the lights were working; pipes were admitting heat, the heat mats and checked temperatures for the Priva system. The system showed us the temperatures climbs and dips over 24 hours. We walked the crop making sure we didn’t leave any unhappy plants unnoticed. After all the morning opening duties were complete we began by cleaning out the seed fridge. We pulled out all the drawers and containers wiped down and sterilized the fridge and attempted to put it all back together, which apparently was easier said than done, we quickly moved on to cleaning out the propagation by chamber removing all the cuttings out and placing them on tables in the potting room. After the chamber was clean, sterilized and as much of the algae taken off possible we placed the cuttings back into their cozy little environment. Sean and I then grabbed some stock baskets for Cuddy farms and took some cuttings for plants to be used in summer. We began by cutting the plants, dipping them in rooting hormones and placed them in cutting mix soil (2/3 mix HP and 1/3 perlite), watered the cuttings, labelled them, updated the stock inventory, and placed them in the germination chamber to start growing roots. Even though it seemed gloomy and cloudy all day we watered the succulents and Cannas as they needed little watering. After a hardy pizza lunch we took the Aquamate to the library and book store and watered the Ficus and under-story plants. We also treated them for mealy bug and cleaned all the dust off the leaves allowing them to take in more sunlight energy. Near the end of the day we had a visit from a fellow horticulture classmate to boost our energy and began our cleanup for the day.






   
Sunday February 13th 2017
Today Sean and I arrived to the greenhouse ready to work. The weather was crummy with its freezing rain and snow mix .We certainly didn’t think mother nature was too happy today - maybe the thoughts of the upcoming Valentine’s Day was getting to her. We began with opening the greenhouse and completing all out our tasks without any problems. We finished staining the trellises needed for Cuddy farms in the spring and started right away with cleaning and organizing all the pots and trays in our tractor bay. After what seemed to have been millions of pots and trays we had finally placed each item on its proper shelf and labelled them. Lunch time today was a little later than usual but that didn’t seem to bother the two us and began our final hours of weekend duty. While filling the wash sinks we noticed we had no hot water! And quickly checked the greenhouse pipes to make sure they were still supplying heat for the crop. We informed Jeff of the incident and went on with our duties. At the end of the day it was time to get any other jobs completed. We wrote the IPM report for the weekend, this blog entry and finished cleaning out the catch basins. The floor drains in the greenhouse were pretty dirty so we decided to wash them out including the drain in the potting room. In our final hour of greenhouse weekend duty we had uploaded pictures to the stock basket inventory and re labelled pictures on the USB drives.










Tuesday, February 7, 2017

WEEKEND BLOG – February 3-5, 2017
By: Alison & Justin
Our weekend duty has been a lot of organizing and taking inventory within the Fanshawe greenhouse. On Friday morning we got started with our greenhouse check list. Watering, checking the temperatures, the humidity and opening the cash for Friday sales were some of the items on the list. Our program coordinator Michael Pascoe came into the greenhouse and asked us to make up succulent pots for the Plant Symposium coming up on Feb 17th. For those of you that don’t know what that is, it is a horticulture event where people talk about flowers and plants. Justin and I had to make up 25 pots with around 4 succulents in them, with a decorative white stone on top. This task took most of Friday keeping the tags in line with the correct pot, and potting up certain succulents with others. These pots will enhance Fanshawe’s reputation - showing off all we have learned.








 After the succulent pots were complete we had 2 massive Aloe plants to re pot for the same horticulture show. We placed them into two decorative pots with the white decorative stone on top.



To end Friday off, we began to organize the 2 benches in the greenhouse for our sales shelf. Organizing included moving the 4 inch annual pots and keeping the same annuals together and then we had to keep the small succulents together. We decided to keep the variegated lavender scallops on the top shelf as they can be viewed from standing.

Saturday morning started out with the biggest job on our weekend duty. We had to go through all the stock baskets and organize them by their watering requirements. Each plant was tagged as green, yellow or red. Green means it likes water and needs a lot, yellow means it can be left a few days and still survive if it doesn’t get water for a day or so. Yellow also means it doesn’t like too much water or to be over watered. We have a very few plants categorized as red which means that they don’t like to be over watered and need to dried out in between watering. After researching each plant and typing out a label for it, we had organized them in the greenhouse on 3 benches by watering requirements. If there was more then one of the same plant, we had to make sure they were grouped together. The next step was to take pictures of each individual stock basket and upload them to a USB. Now for future reference we have information on all the plants we have in stock! Around lunch time, we went into the school to water the 3 tree Ficus in front of the book store and take off a few of the yellowing leaves. 



Next stop were the Spider plants in the hallway of M building to water.



 As yesterday was very sunny for a change, we walked the crop (Hydrangeas) around 3 and noticed the hydrangeas were very dry, even though they were watered in the morning so we decided to water them. Then to end Saturday night off we did a bit of cleaning in the greenhouse and potting room.

Sunday morning started off very cold and snowy which is a big change from Saturday. As we did our morning check list and walked the crop, we noticed the hydrangeas were still very moist from our late watering Saturday evening, so we chose not to water the crop this morning except for then the seed flats, poinsettias, and annuals that needed it. After walking the crop and watering, our next task on the list was to pot up 50 geranium cuttings. The perennial geraniums were dug out of the ground from the campus beds in the summer. We were to cut them off and get a good root systems and put 2-3 in a pot. We propagate these because instead of spending money on new ones, why wouldn’t you use the ones you already have. It’s the smart way to garden!! After the geraniums were done, we transplanted 4 pack annuals into 4” pots, and put these out into greenhouse. We did our second crop walk around 1 o’clock and made the decision to water the hydrangeas. In our greenhouse class on Wednesday morning we were instructed to do an aluminium sulfate drench to the Blue hydrangeas. The drench will change the pH in the plant which will help make the flower to come out as a purer blue. However, the scale we used to measure the correct amount of aluminum sulfate was out of whack and it was too far gone before we could change anything. Our duty over the weekend was to monitor the Blue hydrangeas’ pH and E.C. readings. We also decided to water the Blue hydrangeas with the watering can since it will flush the plant out better rather than the emitters. All in all, good weekend in the Fanshawe greenhouse!

Friday, February 3, 2017

January 27 - 29, 2017 Weekend Duty Blog
Jihyun and Brett

Jan 27th
On Friday January 27th, we started our weekend duty by starting our morning check list which included taking greenhouse temperatures and walking the crop, and checking PRIVA for temperature settings. After our check list was completed we began to transplant Pennisetum grasses into 1 liter pots. We had to check all the grasses for dead reeds and grass blades and clean them out. If the grass had too much dead material, we had to compost them. In the end, we had a total of 219 grasses.


After the grasses were done we had to make new fertilizer for the blue hydrangeas. We haven’t made it before so Jeff came and showed us how. With this fertilizer, we needed 1666 grams to put into our 10 liters of water. Since we had all of the fertilizer mixing tools out we also needed to make new stock basket fertilizer which was a 20 – 20 – 20 fertilizer, to make this we needed 500 grams for 10 liters of water.



Jan 28th
Our second day started the same as before by checking off our morning check list. After our check list was done we finished taking spider plant off shoots and placed them in the green house with a plastic covering. After that was all done we had to change some emitters on bench 11. The emitters were not emitting water as they should have so we took them off completely and placed the old ones in a hot water bleach solution to soak. We then put the new ones on and placed them in the hydrangeas.
After lunch, we went to F hall and to the library to water and cut any dead wood away for the tropical plants. They were pretty dry but there was hardly anything to clean out of them. When we got back to the greenhouse  we made some cuttings out of the German ivy in the green house and put them in a flat covered in a clear plastic cover to keep the moisture in.

Jan 29th
We started our day by doing our morning check list and walking the crop. In our walk, we decided that the crop needed to be watered. So, we started with the blue hydrangeas and set up the dosatron to use the blue fertilizer. After the blue hydrangeas had enough water we switched to the other hydrangeas and switched to the appropriate fertilizer. We then spot watered any plants that were dry in the green house with a watering can. After lunch, we decided to clean the entire greenhouse, we washed all the floors with the hose and squeegee. We also cleaned the tables off with a rag soaked in water and a bit of bleach.


After the floors were done we had gathered a lot of compost from the weekend so we took the RTV out with the compost and dumped it into the compound. Then to finish the weekend we did our closing checklist and locked up.